Construction planning

ISO & NEN

All our datacenters are ISO27001 & NEN7510 certified.

Construction planning

The InterDC datacenter will be build in 3 construction phases:

Phase1:
Datafloor with 20 racks
Power: Ups System, Single feed
Fireprotection: Co2 extinguishers
Cooling: Free Air koeling & Uniflair airco
Fiber: Single fiber
Expected completion date: 30 june 2011
Status: Ready

Phase2:
Datafloor with 40 racks
Power: UPS system, A+B feed
Fireprotection: Vesda system, CO2 extinguishers
Cooling: Free Air koeling & Uniflair airco
Fiber: Single fiber + Backup
Expected completion date: 31 december 2011
Date of completion: 25 june 2012
Status: Ready

Phase3:
Datafloor with 60 racks
Power: UPS system (N+1), A+B feed, generator
Fireprotection: Vesda system, CO2 extinguishers
Cooling: Free Air koeling & Uniflair airco
Fiber: 4 geographical redundant fibers
Expected completion date: 31 march 2014
Date of completion: 25 january 2016
Status: Ready

When phase 3 is completed, InterDC will be certified as Tier3 datacenter.

Datacenter Enschede
  • InterDC Enschede Haven
  • Josinkstraat 30
  • 7547AB Enschede
  • The Netherlands
Datacenter Enschede
  • InterDC Enschede Marssteden
  • Marssteden 110
  • 7547TD Enschede
  • The Netherlands
Datacenter Hengelo
  • InterDC Hengelo
  • Sherwood Rangers 1
  • 7551KW Hengelo
  • The Netherlands
Datacenter Doetinchem
  • InterDC Doetinchem
  • Gildenbroederslaan 1
  • 7005BM Doetinchem
  • The Netherlands